The context
Paddington is a flagship station on the London Crossrail (Elizabeth line) project. Our client, an M&E subcontractor, was delivering the station fit-out, and we took responsibility for both the main contract programme and the short-term delivery planning.
The challenge
External:
- Drip feeding and constant changing of design
- Frustrated access to work fronts
- Constant design changes requiring significant rework
Internal:
- Day-to-day planning that needed a shared rhythm across teams
- A gap between the project schedule and the work happening at the front
- Progress that was hard to read week to week
- Delays and their causes that needed capturing as they happened
What changed
It is extremely important that processes on projects take into consideration the human element. It only takes one simple problem in the design or execution of the process to completely destroy the value of it through loss buy-in of key team members. Typical examples of this are using difficult to read Gantt chart software or poorly facilitated meetings that fail to maintain focus. It is critical that information is communicated clearly in a way the customers of the information (usually the site delivery managers and foremen) can understand.
The workflow was carefully designed in close consultation with the project team, taking into account the unique challenges of the project and human psychology. Simple coloured layouts were used in conjunction with easy to read charts and tables.
Outputs:
- 2-week look-ahead tied into the master programme – ensured that critical information that had been captured by the project managers and planners was taken into account at the work front.
- Capture of all blockers and assigning actions to clear them and raise early warnings/compensation events for external delays.
.png)
Outcomes
- Clarity on blockers ensuring speedy close out of internal issues and early warnings raised for external issues
- Enhanced communication between project team and specialist subcontractors
- A clear plan for the next 2 weeks of work based on consensus
- Correct work sequence was guaranteed by linking the 2-week plan to the contract master programme
-
.png)
Lessons from the programme
As a contractor/subcontractor you often have a large amount of external dependencies which you have no control over. However, implementing a well designed weekly delivery management cycle can ensure that you keep your own house in order and that you are able both deliver effectively and protect yourself commercially.