Building a 2-week plan the whole team agreed on at Crossrail Paddington

We optimised execution of the works on this flagship project by implementing weekly delivery planning for all mechanical and electrical (M&E) works in a live station environment.

The context

Paddington is a flagship station on the London Crossrail (Elizabeth line) project. Our client, an M&E subcontractor, was delivering the station fit-out, and we took responsibility for both the main contract programme and the short-term delivery planning.

‍

The challenge

‍

External:

‍

Internal:

‍

What changed

It is extremely important that processes on projects take into consideration the human element. It only takes one simple problem in the design or execution of the process to completely destroy the value of it through loss buy-in of key team members. Typical examples of this are using difficult to read Gantt chart software or poorly facilitated meetings that fail to maintain focus. It is critical that information is communicated clearly in a way the customers of the information (usually the site delivery managers and foremen) can understand.

The workflow was carefully designed in close consultation with the project team, taking into account the unique challenges of the project and human psychology. Simple coloured layouts were used in conjunction with easy to read charts and tables.

‍

Outputs:

‍

‍

Outcomes

‍

Lessons from the programme

As a contractor/subcontractor you often have a large amount of external dependencies which you have no control over. However, implementing a well designed weekly delivery management cycle can ensure that you keep your own house in order and that you are able both deliver effectively and protect yourself commercially.