Stabilising a delayed enabling works package at HS2 Euston Station

We were engaged by a specialist subcontractor to recover a project that was in significant delay, exposing our client financially. In turn, we tackled the delayed project using our “Engine Room” approach.

The challenge

‍‍

A series of unresolved contractual issues

A formal contract programme and agreed key dates were still to be established, and the contractual record, notifications issued and meeting minutes kept, gave differing accounts of the delay periods experienced.

It also faced a complete re-design, re-sequence, and re-price, requiring agreement.

‍

What changed

‍

Integrating the commercial & planning functions

This project provided the perfect opportunity to deploy our “Engine Room”, an integrated approach to planning and commercial management, delivered by a multi-disciplinary team.

Combining these services is our antidote for removing the communication barriers that widely exist between commercial and planning staff, increasing efficiency and thus reducing costs. On this project we:

‍

‍

Outcomes

‍

Account recovered in full with further savings made too

Our methodological approach, transparent workings, and substantiation using site records, left the end client with no option but to agree to a Final Account that represented a 259% increase versus contract value, inclusive of a 1-year Extension of Time (EOT). This generated a very profitable outcome for our client; a remarkable feat considering the starting point.

This unique approach to consulting saved time and money, therefore having enormous potential for any future clients willing to adopt this out-of-the-box delivery method (enabled by our multi-disciplined professionals).

‍