Case Study

Building a contract programme that kept pace with change on a £20m NEC3 package

We delivered a detailed contract programme and proactive delay claims for a £20m mechanical and electrical (M&E) installation under an NEC3 contract.

The context

The Northern line was being extended to the Vauxhall, Nine Elms and Battersea areas. Our client was contracted to deliver the M&E fit-out works under an NEC3 Fixed Cost contract.

‍

The challenge

‍

What changed

‍

Programme Management

The programme was broken down into the lowest level of detail required to demonstrate delay. This was every work area where there may be design or access issues. We ensured client dependencies and blockers were clearly defined on the Programme for acceptance with the critical path clearly defined and client delay explained in programme narrative.

This allowed us to clearly communicate the knock on effects of the client delays to the rest of the project so that they understood the basis of the compensation events.

‍

Data Analytics

We deployed an extensive Power BI analytics app that gave the project team access to their programme data, earned value, blockers lists, contractual communications and more. It tied the data sets together to provide the project manager with a kind of command centre that allowed him to see what the key areas were that he should focus on.

‍

‍

Outcomes

‍

‍

Lessons from the programme

When it is clearly shown on the programme there is no argument when it comes to compensation events. This allows an easy agreement with the client as well as water tight evidence if things evolve into an adjudication scenario.

Need a contract programme that keeps pace with design and access changes? See how we build one.