The context
Gigafactories are a complex building type: enormous, technically dense, and driven by production deadlines that hardly move. Construction, equipment installation, and commissioning are tightly sequenced. A delay in one phase affects everything that follows.
AESC engaged us as Planning Consultant to develop and manage the Integrated Master Schedule. What started as a scheduling engagement grew into a broader programme management partnership, including Level 4 schedules to support site-level activity management.
One programme, one picture
Delivering a gigafactory at this scale means managing multiple contractors, tightly sequenced workstreams, and production deadlines that hardly move. AESC recognised that a programme this complex needed one integrated schedule: a single source of truth that all parties could work from, current enough to drive daily decisions and detailed enough to support senior reporting. They brought us in to build it with them.
What changed
One schedule, updated weekly, used across the project
We developed an Integrated Master Schedule at Level 4, a single, end-to-end view of the entire programme. With dependencies and integrated milestones visible across the whole programme, the schedule could do more than track what had happened — it gave the team a reliable forward view of where things were heading, at every level from site to senior management.
Controls that feed into every decision
Around the IMS we introduced a structured project controls rhythm: weekly progress meetings to surface risks early, coordination routines to align stakeholders, and regular reporting that kept top management informed on programme status. Decisions at every level were grounded in schedule evidence.
.png)
Capability built to last
As the engagement matured, we developed detailed Level 4 schedules for site-level activities and ran workshops and training to build planning discipline across AESC’s own team. The aim was for AESC’s planners to understand and manage their schedules independently. Project controls is now embedded in how AESC runs the programme, driven by their own team.
.png)
.png)
Outcomes
- An Integrated Master Schedule - the programme's single source of truth, connecting every workstream into one forward view
- Level 4 site-level schedules driving day-to-day monitoring of construction, equipment installation, commissioning and production activity
- A weekly reporting and coordination rhythm adopted from field teams through to senior management
- Planning capability embedded in AESC’s own team through structured training and knowledge transfer
- Planning embedded as an organisational priority, with a foundation they can build on for future programme
-