Building a contract programme that tracked every scope change at the Houses of Parliament

We ensured pro-active delay claims by developing a detailed contract programme and capturing all scope changes as they occurred.

The context

The project was a communications installation around the Houses of Parliament Estate. It involved 24/7 shifts in public areas and a defined traffic control period within which the work had to be completed.

‍

The challenge

‍

What changed

A highly detailed programme and contractually compliant programme was developed. This allowed the team to see what needed to be done every day and helped the commercial team to demonstrate the knock on effect of delay events in the most clear way possible.

‍

‍

Outcomes

‍

‍

Lessons from the programme

Sometimes it is necessary to go down to the very lowest levels of detail on a contract programme. At the end of the day it is a commercial tool and it needs to be built with this in mind so that it is fit for purpose for recovering costs and protecting against delay damages.

Need every scope change captured in your programme as it happens? See how we plan for it.